Project Description

Breakneck Creek Wastewater
Treatment Plant Upgrade

MARS, PA

OWNER:
Breakneck Creek Regional Authority

SCOPE OF WORK:

  • Increase the current plant from 3 MGD to 4.5 MGD
  • 384 Rock Anchors/Tie Downs
  • Construction of Two Concrete SBR, Two Digestor Tanks, Belt Filter Press/Digester Building
  • Modification of existing SBR and digesters, Installation of a new UV disinfection unit, a new mechanical fine screen and grit collector.
  • Associated Site Piping and New Access Road.