Project Description
Latrobe Equalization Tank –
Long Term Control Plan
Latrobe, PA
OWNER:
Latrobe Municipal Authority
SCOPE OF WORK:
- Construction of 6.3 million gallon precast/post-tensioned circular equalization tank.
- Construction of a new pump station and screen room.
- 80,000 CY of Excavation and Backfill
- 370 Rock Anchors/Tie-Downs
- Installation of 12” – 30” sewer lines, vaults, and manholes.